Procurement is the acquisition of goods, services or works from an external source. It is favorable that the goods, services or works are appropriate and that they are procured at the best possible cost to meet the needs of the purchaser in terms of quality and quantity, time, and location.
Wind Power Take Take-off off in the SARI/Energy Region
Project Procurement Methods and Project Development Options
Soren Krohn, ADB Consultant Colombo, 23 September 2010
Roadmap (»to do« List) for Governments 1
Good wind resource near grid & road, road high cost/risk of alternatives? Already demonstration project, interested investors?
NO Demo EPC plant YES
IPP/BOO plant (built by developer)
Competition on kWh price Fixed kWh price
Preassigned g site
IPP/BOO developer p finds site
(requires dispersed resources)
Denmark E Egypt t Germany Mexico Québec Syria Thailand Yemen
Denmark offsh E Egypt t Mexico
E Egypt t Mexico Ontario Québec
Denmark onsh Egypt Germany Ontario
Syria Thailand Yemen
Roadmap (»to do« List) for Governments 2
Good wind resource near grid & road, road high cost/risk of alternatives? Already demonstration project, interested investors?
NO Demo EPC plant YES
IPP/BOO plant (built by developer)
Competition on kWh price Fixed kWh price
Preassigned g site Do transmission grid study for site
Do preliminary env/soc impact study
IPP/BOO developer p finds site
(requires dispersed resources)
Secure land lease option Apply [pay?]
Prequalify developers (tech/econ) Public land or get land lease option Ensure automatic permits/licenses
Do transmission grid study for site
Env/soc impact study by developer
Roadmap (»to do« List) for Governments 3
Preassigned site
EPC IPP/BOO
IPP/BOO developer finds site
(requires dispersed resources)
Do transmission grid study for site
Do preliminary env/soc impact study
Secure land lease option A l [ Apply [pay?] ?]
P Prequalify lif developers d l (tech/econ) (t h/ ) Public land or get land lease option Ensure automatic permits/licenses Wind measurement
Do transmission grid study for site
Env/soc impact study by developers
Wind measurement by developers…
…jointly …individually
All local wind measurements also need regional long-term wind data! Energy assessment Energy assesment by developers
Roadmap (»to do« List) for Governments 4
----------------------------------- IPP/BOO ----------------------------------------- Competitively tendered price ------ ----- Fixed price ------------------ Preassigned site -------------------------- Developers find site ------------------- EPC ---------
Do wind D i d measurement
Wi d measurement Wind tb by d developers… l
…jointly …individually
All local wind measurements also need regional long-term wind data! Do energy assessment
Do feasibility study Hire owners' consultant Tender for EPC contractor
Energy assesment by developers
Hire consultants to draft RFP for PPA Issue RFP for wind elecricity purchase
Std. PPA & grid connection rules exist?!
Feasibility study by developers Bids for kWh price by developers Fixed kWh price
Roadmap (»to do« List) for Governments 5
----------------------------------- IPP/BOO ----------------------------------------- Competitively tendered price ------ ----- Fixed price ------------------ Preassigned site -------------------------- Developers find site ----------Hire owners' consultant Tender for EPC contractor Feasibility study by developers Bids for kWh price by developers Fixed kWh price --------- EPC ---------
Verify wind resource (energy) assessment For safety & performance: Verify compliance with IEC 61400, latest edition Verify compliance with existing grid code for wind turbines & wind farms Issue other permits automatically Get permits
Sign Power Purchase Agreement for 20 years = IEC certification
Th k You Thank Y
Contact details Soren Krohn
Wind Energy Consultant, Washington DC Phone +1 +1-202-468-2902 202 468 2902
Email [email protected]
doc_735973873.pdf
Procurement is the acquisition of goods, services or works from an external source. It is favorable that the goods, services or works are appropriate and that they are procured at the best possible cost to meet the needs of the purchaser in terms of quality and quantity, time, and location.
Wind Power Take Take-off off in the SARI/Energy Region
Project Procurement Methods and Project Development Options
Soren Krohn, ADB Consultant Colombo, 23 September 2010
Roadmap (»to do« List) for Governments 1
Good wind resource near grid & road, road high cost/risk of alternatives? Already demonstration project, interested investors?
NO Demo EPC plant YES
IPP/BOO plant (built by developer)
Competition on kWh price Fixed kWh price
Preassigned g site
IPP/BOO developer p finds site
(requires dispersed resources)
Denmark E Egypt t Germany Mexico Québec Syria Thailand Yemen
Denmark offsh E Egypt t Mexico
E Egypt t Mexico Ontario Québec
Denmark onsh Egypt Germany Ontario
Syria Thailand Yemen
Roadmap (»to do« List) for Governments 2
Good wind resource near grid & road, road high cost/risk of alternatives? Already demonstration project, interested investors?
NO Demo EPC plant YES
IPP/BOO plant (built by developer)
Competition on kWh price Fixed kWh price
Preassigned g site Do transmission grid study for site
Do preliminary env/soc impact study
IPP/BOO developer p finds site
(requires dispersed resources)
Secure land lease option Apply [pay?]
Prequalify developers (tech/econ) Public land or get land lease option Ensure automatic permits/licenses
Do transmission grid study for site
Env/soc impact study by developer
Roadmap (»to do« List) for Governments 3
Preassigned site
EPC IPP/BOO
IPP/BOO developer finds site
(requires dispersed resources)
Do transmission grid study for site
Do preliminary env/soc impact study
Secure land lease option A l [ Apply [pay?] ?]
P Prequalify lif developers d l (tech/econ) (t h/ ) Public land or get land lease option Ensure automatic permits/licenses Wind measurement
Do transmission grid study for site
Env/soc impact study by developers
Wind measurement by developers…
…jointly …individually
All local wind measurements also need regional long-term wind data! Energy assessment Energy assesment by developers
Roadmap (»to do« List) for Governments 4
----------------------------------- IPP/BOO ----------------------------------------- Competitively tendered price ------ ----- Fixed price ------------------ Preassigned site -------------------------- Developers find site ------------------- EPC ---------
Do wind D i d measurement
Wi d measurement Wind tb by d developers… l
…jointly …individually
All local wind measurements also need regional long-term wind data! Do energy assessment
Do feasibility study Hire owners' consultant Tender for EPC contractor
Energy assesment by developers
Hire consultants to draft RFP for PPA Issue RFP for wind elecricity purchase
Std. PPA & grid connection rules exist?!
Feasibility study by developers Bids for kWh price by developers Fixed kWh price
Roadmap (»to do« List) for Governments 5
----------------------------------- IPP/BOO ----------------------------------------- Competitively tendered price ------ ----- Fixed price ------------------ Preassigned site -------------------------- Developers find site ----------Hire owners' consultant Tender for EPC contractor Feasibility study by developers Bids for kWh price by developers Fixed kWh price --------- EPC ---------
Verify wind resource (energy) assessment For safety & performance: Verify compliance with IEC 61400, latest edition Verify compliance with existing grid code for wind turbines & wind farms Issue other permits automatically Get permits
Sign Power Purchase Agreement for 20 years = IEC certification