A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
A.
1/4
B.
1/10
C.
7/15
D.
8/15
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
A. 12 days
B. 15 days
C. 16 days
D. 18 days
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
A. 20 days
B. 22 1/2days
C. 25 days
D. 30 days
A.
1/4
B.
1/10
C.
7/15
D.
8/15
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
A. 12 days
B. 15 days
C. 16 days
D. 18 days
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
A. 20 days
B. 22 1/2days
C. 25 days
D. 30 days