Test paper Project Management Sem 1

Q 1. Discuss merits and demerits of Matrix type of project organization.

Q 2. DIscuss major merits of network diagram in scheduling the project.

Q 3. Describe the important characteristics of a good project control system.

Q 4. Given the following network (time in days)

Activity

Crash Time, Cost

Nominal time cost

Partial crashing

a

3, $60

3, $60

No

b

6, $80

7, $30

Yes

c

2, $90

5, $50

No

d

5, $50

6, $30

No

e

2, $100

4, $40

Yes

Find lowest cost to complete the project in 10 days.

Q 5 Write short notes on any two of the following

a. Multiproject scheduling and resource allocation.

b. Human ns financial resources control in projects.

c. Selection of project organizational structure.
 