Q 1. Discuss merits and demerits of Matrix type of project organization.
Q 2. DIscuss major merits of network diagram in scheduling the project.
Q 3. Describe the important characteristics of a good project control system.
Q 4. Given the following network (time in days)
Activity
Crash Time, Cost
Nominal time cost
Partial crashing
a
3, $60
3, $60
No
b
6, $80
7, $30
Yes
c
2, $90
5, $50
No
d
5, $50
6, $30
No
e
2, $100
4, $40
Yes
Find lowest cost to complete the project in 10 days.
Q 5 Write short notes on any two of the following
a. Multiproject scheduling and resource allocation.
b. Human ns financial resources control in projects.
c. Selection of project organizational structure.
Q 2. DIscuss major merits of network diagram in scheduling the project.
Q 3. Describe the important characteristics of a good project control system.
Q 4. Given the following network (time in days)
Activity
Crash Time, Cost
Nominal time cost
Partial crashing
a
3, $60
3, $60
No
b
6, $80
7, $30
Yes
c
2, $90
5, $50
No
d
5, $50
6, $30
No
e
2, $100
4, $40
Yes
Find lowest cost to complete the project in 10 days.
Q 5 Write short notes on any two of the following
a. Multiproject scheduling and resource allocation.
b. Human ns financial resources control in projects.
c. Selection of project organizational structure.