Information Flow

Process Diagram
Stretcher / Wheel Chair Receptionist

MRI Technologist

Process Flow

5%

Explain about MRI Process

Patient check with receptionist Customer

Patient wait for MRI Tech

Physically Handicap

95%

Check fitness for MRI

85%

Apparel with metal

75%

Magnet Room

Paper Work verification

25% (Exit) 15%

Need to change clothes

MRI Scan starts Patient escorted back to front desk
75%

Machine Setup

(Exit)

Clothes check

Technologist prints scan

25%

Handing Printouts to radiologists

Feeds data during scan

Clothes Changed

• Poor communication between patient and the scheduling department • Patients are not being screened properly before coming to the MRI scan • Sinclair’s training on different MRI machine. • Poor Process Design • Overloading of MR Technologist

Information Flow

MRI Technologist

Process Flow

Stretcher / Wheel Chair Receptionist

5%

Explain about MRI Process

Patient check with receptionist Customer

Patient wait for MRI Tech

Physically Handicap

95%

Check fitness for MRI

85%

Apparel with metal

75%

Magnet Room

Paper Work verification

25% (Exit) 15%

Need to change clothes

MRI Scan starts Patient escorted back to front desk
75%

Machine Setup

(Exit)

Clothes check

Technologist prints scan

25%

Handing Printouts to radiologists

Feeds data during scan

Clothes Changed

Processes

Escort the patient to the Magnet Room Changing Room Verify Paperwork Positioning of Coil MRI Scan Data Entry Printing MRI Scans Escort the Patient back to Front Desk Changing Room

Time Consumed (Minutes) 5 4 1 4 16.5 1 6 2

4

MR Technologist

MR Assistant

MR Technologist brief Positioning the coil Tunnel ( for 30 min schedule ) Printing Total

1 min 4 minutes 16.5 minutes 6 minutes 27.5

MR Technologist

Initial Health check up Changing clothes

5 minutes 8 minutes 2 minutes 15 minutes

MR Assistant

Escorting back Total

Arrival

Departure

Patient 1 Patient 2 Patient 3 Patient 4 Patient 5 Patient 6 Patient 7

7:45 7:45

8:30 9:00

8:15
8:45

9:30
10:00

9:15
9:45 10:15

10:30
11:00 11:30 Patient 8 Patient 9 Patient 10 Patient 11 Patient 12 Patient 13 Patient 14
Arrival Departure

10:45
11:15 1:15 1:45 2:15 2:45 3:15 3:45

12:00
1:30 2:00 2:30 3:00 3:30 4:00 4:30

Patient 15

Throughput time for Customers Final
Capacity utilization of machine initial Capacity utilization of machine After Idle Time for Machine initial (minutes) Idle Time for Machine Final (minutes) Decrease in idle time in %

75 minutes
50% or less 100% 38.5 8.5 77.92207792

Patient 1 Process of Patient 2 has started in parallel

Process for Patient 2 3 has Patient started and Patient 1 is in the Magnet Room

Patient 3

Moving 45.34% Customer 47.37% 7.28% Waiting Operation Customer 9.35% 52.67% 37.98%

Moving Waiting

Operation

0.00% 20.00%40.00%60.00%80.00% 100.00%

0.00%

50.00%

100.00%

• Increased Revenue

• Greater Utilization

• No Overtime

• Customer Satisfaction



doc_950643606.pptx
 