Case Study on Capital Budgeting and Initial Cash Outlay (ICO) Uncertainty

Description
In finance, the net present value (NPV) or net present worth (NPW)[1] of a time series of cash flows, both incoming and outgoing, is defined as the sum of the present values (PVs) of the individual cash flows of the same entity.

Case Study on Capital Budgeting and Initial Cash
Outlay (ICO) Uncertainty

Abstract
According to recent surveys, most companies use discounted-cash-flow (DCF) methods to
evaluate capital budgeting decisions. DCF methods typically assume that a project's initial
cash outlay (ICO) is known with certainty. However, many types of initial outlays have
substantial uncertainty, especially those involving the construction of a new facility. This risk
affects not only the ICO, but it also affects subsequent depreciation tax shields. A proper capital
budgeting analysis should incorporate the additional risk that is due to an uncertain ICO. We
show that neither the typical practices employed by corporations nor two common techniques
advocated in the finance literature, risk-adjusted discount rates and certainty equivalents,
satisfactorily address ICO risk. Sensitivity analysis is an effective way to address ICO risk, but
the finance literature often overlooks the adjustments needed to satisfactorily address ICO risk
within a sensitivity analysis. We fill this gap in the literature by showing the impact of ICO risk
on the standard deviation of a project's NPV. We then apply sensitivity analysis with the
appropriate adjustments in a numerical example to illustrate the impact of ICO risk.


I. Introduction
According to surveys, most companies use discounted-cash-flow (DCF) methods to evaluate
capital budgeting decisions.
1
DCF methods typically assume that a project's initial cash outlay
(ICO) is known with certainty. However, many types of initial outlays have substantial
uncertainty, especially those involving the construction of a new facility. In addition, this risk
affects not only the ICO, but it also affects subsequent depreciation tax shields. A proper capital
budgeting analysis should incorporate all of the additional risk that is due to an uncertain ICO.
Unfortunately, the typical "contingency" approach employed by many corporations does not
satisfactorily address ICO risk. The academic literature also has not satisfactorily addressed ICO
risk. For example, two common techniques advocated in the finance literature, the use of
certainty equivalents and risk-adjusted discount rates, require too much subjectivity to be useful.
Sensitivity analysis is an effective way to address ICO risk, but the finance literature often
overlooks the adjustments needed to satisfactorily address ICO risk within a sensitivity analysis.
Following is a more detailed discussion of the practitioner and academic shortcomings related to
assessing the risk of an uncertain ICO.

A recent survey by the CFO Executive Board indicates that companies believe ICO uncertainty
is important and that companies try to address it in their capital budgeting analyses.
2
Most


1
2


For example, see Bierman (1993) or Graham and Harvey (2001). See
CFO Executive Board (2005).



companies adjust the estimated initial cash outlay by adding a "contingencies" amount to the
original cost estimate.
3
For example, if the estimated cost of the project is $10 million, then the
firm might create a contingencies account equal to $100,000, resulting in a total adjusted initial
cost of $1.1 million, which is used when computing the project's net present value and internal
rate of return. If actual costs exceed the adjusted ICO, based either upon a dollar basis or a
percentage of the adjusted ICO, then many companies require the project to go through a re-
approval process. There are two shortcomings to this practice. First, the trigger for re-approval
analysis should be based upon the expected net present value of the project (given the cost
overrun) and not upon a pre-determined dollar amount or percentage. For example, a cost
overrun of 10 percent might cause one project's NPV to become very negative, while it might
have only a small impact on another project's NPV. Second, because there is no theoretical
basis for estimating the appropriate amount that should be included in the contingencies account,
the contingencies account becomes only an educated guess.

The academic literature for assessing risk includes the certainty equivalent approach, the risk-
adjusted discount rate approach, and sensitivity analysis.
4
A "certainty equivalent" is the certain
amount that one would be willing to take in lieu of a risky cash flow. For example, consider a
coin toss in which you must pay $100 for heads and $200 for tails. The expected cost is $150,
but it is very risky. To avoid this risk, you might be willing to pay a sure $155 rather than take
the risky coin toss, even though the sure $155 costs more than the expected $150 cost of the coin
toss. With respect to ICO risk, one could, in theory, estimate the certainty equivalent cash
outflow for each uncertain (risky) ICO component, based on the expected cash flow and its risk,
and use this certainty equivalent rather than the estimated ICO when estimating the project's
NPV.
5
Notice that this is very similar to the common practice described above of increasing the
ICO by a contingencies account, where the adjusted ICO is essentially a certainty equivalent. In
the example above, the adjusted cost of $1.1 million is equivalent to a certainty equivalent for
the risky $1 million cost.

Unfortunately, there are no theoretical guidelines for estimating the certainty equivalents that
would be chosen by the firm's shareholders. In other words, there is no way to determine the
sure, but more costly, cash flow that a shareholder would be willing to pay in lieu of the risky
ICO.

An additional complication to the certainty equivalent approach is that many initial outlay
components add to the depreciable basis of the project. If the depreciable basis of the project
changes due to a change in the ICO, then the future tax-shield benefits due to depreciation will
also change. This means that the certainty equivalent becomes the sure amount you are willing
to pay now to avoid the combination of a risky cash flow (the ICO) and the present value of the


3


Some companies use the term "contingencies" as a catch-all for many estimated small costs. In other words, some
companies would rather list a single account called "contingencies" rather than numerous small accounts. Other
companies use the term "contingencies" for unknown costs that might occur. It is this second use that we address.
4

Scenario analysis and simulation are two other techniques to assess risk. We focus upon sensitivity analysis, but our
adjustments can easily be extended to scenario analysis and simulation.
5
If the ICO occurs at some other time than zero, then the certainty equivalent would be discounted at the risk-free
rate.
2



depreciation tax shield. This multiple-period spillover effect further complicates any realistic
use of certainty equivalents when dealing with uncertain ICO components.

A second technique often advocated in the finance literature is the use of risk-adjusted discount
rates. For example, if two future expected cash flows have different degrees of risk, then a
higher (i.e., risk-adjusted) discount rate might be applied to the riskier cash flow. Similar to the
problem with certainty equivalents, there is often no way to determine the risk-adjustment that
would be preferred by shareholders.
6
A second problem is that the ICO is by definition assumed
to occur at time zero (or at least it is assumed to occur one year prior to the cash flow at the end
of the project's first year). Even if one were to assume that the initial cash flow occurs over
some fraction of the project's first year, the present value of a cash flow occurring a short time in the
future is close to the actual value of the cash flow irrespective of discount rates.
7
Therefore, the
risk-adjusted discount rate technique does not satisfactorily address ICO risk.

In a traditional sensitivity analysis, the estimated expected values of input variables are varied
one at a time with a series of "what if" questions. The original set of estimates for input
variables is called the base case. As an input variable's estimate is changed from its value, its
impact on a project's performance measures, such as net present value (NPV) or internal rate of
return (IRR), can be determined. For example, a typical sensitivity analysis might involve
changes in the number of units sold, the price per unit, the cost per unit, etc. As we show in this
paper, it is possible for a sensitivity analysis to capture the impact of ICO risk, but only if the
analysis properly accounts for the multi-year spillover effect due to the depreciation tax shield.
8


In summary, the typical corporate practice of using contingency accounts fails to satisfactorily
address ICO risk. The certainty equivalent approach and the risk-adjusted discount rate
approach are inappropriate. Sensitivity analysis can accommodate ICO risk if the depreciation
tax shield is appropriately incorporated, but existing textbooks do not articulate this















6
7
















In some circumstances it is possible to make a theoretically correct adjustment. See Daves and Ehrhardt (2000).
This assumes a reasonable discount rate (for example, one between 3% and 25%) is used.
8
Virtually all finance textbooks include examples of sensitivity analysis, but, to the best of our knowledge, only a
couple even tangentially address ICO in a sensitivity analysis. Those exceptions typically provide a numerical
example showing variation in NPV with respect to changes in several variables, including the ICO. However, their
explanation and discussion do not explain the impact that the resulting depreciation tax shield has on NPV and risk.
3



aspect of risk in their examples. We fill this gap in the literature by showing how ICO risk
affects the standard deviation of NPV.

Section II provides a more detailed discussion of the sources of ICO uncertainty. Section III
explicitly identifies the risk due to the multi-year spillover of the depreciation tax shield.
Section IV illustrates appropriate sensitivity analysis with a numerical example.

II. Dealing with ICO Uncertainty

For many capital budgeting analyses, the assumption of a "certain" ICO is valid - e.g., the
purchase of a certain piece of equipment for a fixed price. However, even here, if this equipment
purchase were to require setup and installation, those capitalized expenses could be both sizeable
and uncertain at the time the project is being evaluated. In fact, the larger the project, the more
likely it is to involve a host of uncertain ICO component costs.

In Exhibit 1, we list some of the common items included in the acquisition cost of a firm's major
property, plant, and equipment (PP&E) accounts. Additions to one or more of these accounts
would normally be related to a typical investment project's ICO. Notice how many of the items
listed under the four major PP&E categories - land, land improvements, buildings, machinery
and equipment - could very well have uncertain estimates at the time the project is being
evaluated. Weather conditions, for example, could easily affect land site preparation costs,
building construction costs, and installation costs of equipment involved in a construction
project. In fact, it is the avoidance of just this type of uncertainty that often leads firms to
consider leasing (with its fixed/certain costs) as opposed to building/purchasing with its potential
for cost overruns.

In addition, another typical component of an ICO might be an investment in working capital,
such as inventory. The dollar amounts of such items are unlikely to be known with certainty at
the project evaluation stage, which introduces uncertainty into the ICO.

It is important that managers be able to correctly assess the risk of a potential project, including
the risk due to ICO uncertainty. If the risk is too high, a manager might well choose to forego a
project, even if the expected NPV is positive. The results of an appropriate risk analysis also
allow a manager to identify any appropriate levels of cost overruns that should "trigger" a
complete project re-evaluation. Armed with this information, a manager can then decide
whether any estimates need refining or reviewing, and whether any are not worth investigating
further before deciding on project acceptance/rejection. Based on this analysis, a manager might
decide to remove the uncertainty surrounding a particular ICO input variable by negotiating a
fixed price for some service or outsourcing some in-house, uncertain cost item (like equipment
installation) so as to make it into a certain cost expense. The manager can also identify the
critical levels of cost overruns that endanger the economic viability of the project.





4



The following section identifies the impact of ICO uncertainty on project risk.


Exhibit 1.
Common Items Included in the Acquisition Cost of Property, Plant, and Equipment
_______________________________________________________________________

Land -- Capitalization of land costs include the following -- all of which are not subject to tax
depreciation:
Purchase price
Commissions, permits, or fees paid by the buyer
Closing costs
Cost of real estate surveys
Special assessments for local improvements (e.g., such as pavements, street lights,
sewers, and drainage systems)
Cost necessary to prepare land for its intended use (e.g., grading, filling, draining, and
clearing)

Land Improvements -- Capitalization of land improvement costs include the following -- all of
which are subject to tax depreciation:
Paving
Fencing
Landscaping
Outdoor lighting

Buildings -- Capitalization of building costs include the following -- all of which are subject to
tax depreciation:
Purchase price of an existing building (old or new), or construction costs from excavation
to completion
Expenses incurred in remodeling or altering a purchased building to prepare it for its
intended use
Professional fees (e.g., architectural, engineering, and legal costs) and construction
permits

Machinery and Equipment -- Capitalization of machinery and equipment costs include the
following -- all of which are subject to tax depreciation:
Purchase price
Shipping costs (e.g., freight, import duties, handling charges and insurance on the
equipment while it is in transit)
Sales, use and other taxes imposed on the purchase
Installation costs, including special foundations or plant modifications
Reconditioning (used equipment) and testing for use (used and new equipment)




5




III. ICO Uncertainty and Project Risk: The Impact of the Depreciation Tax Shield
Spillover

Consider a project with an initial cash outlay and expected cash flows at t denoted by CF
t
. If the
project lasts N years and has a cost of capital of r, then the project NPV is:

NPV = - ICO
+
¿
CF
t t N

t =
1
(1+ r)

The initial cash outlay is comprised of a depreciable "Basis" and a portion that might be
nondepreciable, denoted by NonDepr:

ICO = Basis + NonDepr

The cash flow at year t is determined by the project's expected earnings before interest, taxes,
depreciation and amortization (EBITDA
t
), its depreciation (Depr
t
), the tax rate (T), and the
required investment (i.e., the change) in working capital (AWC
t
):

CF
t
= (EBITDA
t
- Depr
t
)(1-T) + Depr
t
- AWC
t


(1)






(2)






(3)

This can be rewritten to separate the impact of EBITDA, the depreciation tax shield benefit, and
the change in working capital:

CF
t
= (EBITDA
t
)(1-T) + Depr
t
T - AWC
t
(4)

Let F
t
denote the depreciation factor for the t
th
year for an asset placed in service at t=0. Let n
denote the depreciation life of the asset, which may be different from the project life N. For
example, under straight line depreciation, the depreciation factor is 1/n. The depreciation factors
for the MACRS tax depreciation method are provided by the U.S. Treasury for each asset class.
For clarity of exposition, we assume that n<=N (i.e., the asset is fully depreciated by the end of
the project life) and that there is no salvage value. The depreciation expense at time t is the
product of the basis and the depreciation factor:

Depr
t
= Basis(F
t
) (5)

The project's NPV can be expressed in terms of the project's ICO, its after-tax EBITDA, the
depreciation tax shield benefits, the investments in working capital, and the project's cost of
capital, r:
9



9



In theory, each source of cash flow (e.g., sales revenue, costs of goods sold, depreciation, etc.) should be
discounted at a rate that is appropriate for the particular risk of that particular cash flow source. In practice (and in
most textbooks), all usual project cash flows are discounted at the project cost of capital. Therefore, we discount all of
the project's cash flows at r. For situations with unusual cash flows, see Daves and Ehrhardt (2003).
6



NPV = - NonDepr - Basis
+
¿
EBITDA
t (1÷ T)
+
¿
Basis
(F
t
)t (T)
÷
¿
A
WC
t
t
N

t =1
(1+ r)
t
n

t =1
(1+ r)
N

t =
1
(1+ r)
(6)

Grouping terms associated with the basis yields:


NPV = - NonDepr - Basis ?1
÷
¿
F
t (T)t
?
n
?
?+

N
EBITDA
t
(1÷ T) ÷
N
AWC
t
??
t
=
1
(1+
r)
?
?
t= ¿
1
(1+ r)
t
¿
1
(1+ r)
t
t=
(7)

Notice the second term in Equation (7) shows that a dollar change in the basis does not cause a
dollar change in NPV, due to the present value of the tax savings due to depreciation. Thus, a
dollar change in the basis produces less than a dollar change in NPV. The depreciation tax
shield also has an impact on the project's risk, as measured by its variance. As we show below,
the tax shield also affects risk. Using Equation (7), the variance of the NPV is:


?


n


?
2
2


N
? (1 ÷ T) o
EBITDA

?
2
+ ?1
÷
¿
F
t T t ?o
Basis
+
¿
?
t
?
o
2
=o
2
NPV NonDepr
?
t
=
1
(1+ r)
?
?
?
(1+ r)
t
?
?

?
2
2
?
t =
1
?
?
?
÷
¿? 1 t
N
?
?o
A
WC
t
+ 2?1
÷
¿
F
t T t n
?
? ? ?
?COV[NonDepr, Basis]
?
t =1? (1 +
r)
?
??
t
=
1
(1+
r)
?

+
2
¿? (1÷ T)t
N
? ?
?
t =1? (1 +
r)
? COV[NonDepr, EBITDA
t
] ?
?

+
2
¿? 1 t
N
?
?
?
t =1? (1 +
r)
? COV[NonDepr,AWC
t
] ?
?

+ 2?1
÷
¿
F
t T t
?
n
?
N
? (1÷
T)
?
?
¿
?
??
COV
[Basi
s,EBI
TDA
t

]
??
t
=
1
(1+
r)
?
t
=
1
? (1+
r)
t
??
?

+ 2?1
÷
¿
F
t T t
?
n
?
N
? 1
?
¿
?
?
? COV[Basis,AWC
t
]
??
t
=
1
(1+
r)
NN
?? ?
t
=
1
?
(1+ r)
t
?
?
? (1÷ T)
?
?? 1
?
+
¿¿

? (1+ r)
t
?
?
?
?
CO
V[
EB
IT
DA
t

,A
W
C
t
]
(8)
t =1 j
?
? ? ?? (1+ r)
t
?

where o
k
denotes the variance of the k
th
source of cash flow and COV denotes the covariance
between the sources of cash flow.

To focus upon the relative contributions to risk due to the ICO and the operating cash flows,
suppose that o
NonDepr
and o
A
WCt, are equal to zero. To simplify the exposition, suppose that
o
EBITDA
is constant for all t. Also assume that all covariances are equal to zero. Under these

7



simplifying assumptions, project risk can be written as:


?


n


?
2
2


?
N
? 1


?

?
2

?
o
2
NP
V
= ?1 ÷ T F
t ??
? (9)
? ?
?
t= ¿
1
(1+ r)
t
???o
Basis
+o
2EBITDA
(1÷ T)
2
?
¿
?
(1+
r)
t
?
t
=1 ?
?
?
?
?
?

Notice in this simplified example, the summation in the second term of Equation (9) is the
present value factor for an annuity of N periods when discounted at the rate r, denoted by
PVIFA
N,r
. Therefore, the risk due to EBITDA is scaled up or down by the present value factor
due to the timing of EBITDA. The longer the life of the project is, the larger the present value
factor is, and the higher the risk due to EBITDA.

Let PVDepr
N,r
denote the summation in the first parentheses above. For the special case of
straight-line depreciation over n years (note that the deprecation life n maybe different from the
project life N), F
t
= (1/n) for nsN and zero otherwise. For straight-line depreciation, PVDepr
N,r

is equal to T/n multiplied by the present value factor for an annuity of n years when discounted
at the rate r: PVDepr
N,r
= (T/n) PVIFA
n,r
. For MACRS depreciation, there is no simple closed
form formula for PVDepr
r
. Using this notation, the variance of expected NPV can be written:

o
2
= (1÷ T PVDepr
n,
r NPV

)
2
o
2Basis

+ (1÷ T)
2
(PVIFA
N,
r
)
2
o
2
EBITDA

(10)


The contribution of ICO risk has two components. The first is due to the initial cash flow. The
second is due to the tax shield benefit provided by depreciation; i.e., T(PVDepr
N,r
). Notice that
this tax shield benefit dampens the risk due to the basis. For example, if the basis becomes
larger, there is a larger cash outflow at time zero, but there is a larger value of the tax shield
benefit. The opposite is true if the basis turns out to be smaller than expected.

Equation 10 provides several insights. First, if an analyst simply ignores the ICO risk (which
implicitly assumes that o
Basis
is zero), Equation 10 becomes:

o
2
= (1÷ T)
2
(PVIFA
N,
r
)
2
o
2

(11)
NPV EBITDA
In this case, the resulting estimate of project risk will be biased downward with respect to the
true risk given in Equation 10.

Second, if an analyst incorporates the ICO risk due to the initial purchase but ignores the
subsequent impact of the depreciation tax shield generated by the ICO (which implicitly assumes
PVDep
N,r
= 0), then Equation 10 becomes:

o
2
=o
2

2

22

(12)
NPV
Basis
+ (1 ÷ T) (PVIFA
N,
r
) o
EBITDA


In this case, the resulting estimate of project risk will be biased upward with respect to the true
risk given in Equation 10. Therefore, to appropriately incorporate ICO risk, the analyst must

8



explicitly consider the depreciation tax shield benefit.

IV. An Illustrative Example of a Modified Sensitivity Analysis for ICO Uncertainty

To illustrate the use of modified sensitivity analysis as it applies to ICO uncertainty in a capital
budgeting analysis, consider the potential purchase of some equipment to be used in a project.
The purchase price is known with certainty to be $600,000. The equipment has a useful life of
five years and is in the three-year property class for MACRS tax-depreciation purposes.
Shipping and installation costs are "estimated" to be $100,000 and $200,000, respectively, and
the equipment has a zero expected final salvage value, five years from now. No additional "net"
working capital is needed. The new equipment will generate estimated additional annual net
operating cash flows, before consideration of depreciation and taxes, of $300,000 a year for five
years. Assuming that the marginal tax rate equals 40 percent, we can estimate the project's
relevant incremental cash flows for the "base case."

IV.A. The Base Case: Net Present Value

Exhibit 2 shows the project's $900,000 initial cash outflow under the "base case."

Exhibit 2.
The Expected Initial Cash Outflow

Equipment cost (certain) = $600,000

+ Capitalized expenditures:

Shipping cost (estimate) = 100,000

Installation cost (estimate) = 200,000

= Initial cash outlay (ICO) = $900,000 = depreciable basis for tax
purposes
















9



Exhibit 3 shows the expected the incremental future cash flows.

Exhibit 3.
Expected Incremental Future Cash Flows
END OF YEAR (in $000s)
_____________________________________________________

1 2 3 4 5

Net change in operating
revenue, excluding
depreciation 300.00 300.00 300.00 300.00 300.00

÷ Net increase in tax
depreciation (299.97) (400.05) (133.29) ( 66.69) --
_______________ _______ _______ _______ _______ ______

= Net change in
income before
taxes .03 (100.05) 166.71 233.31 300.00

÷ (+) Net increase
(decrease) in taxes
(40% rate) (.01) 40.02 (66.68) (93.32) (120.00)
_______________ _______ _______ _______ _______ _______

= Net change in
income after tax .02 ( 60.03) 100.03 139.99 180.00

+ Net increase in tax
depreciation 299.97 400.05 133.29 66.69 --
_______________ _______ _______ _______ _______ _______

= Incremental net
cash flow for
years 1 to 5 299.99 340.02 233.32 206.68 180.00











10



Exhibit 4 combines the ICO from Exhibit 2 with the annual operating cash flows from Exhibit 3,
resulting in the total expected net incremental cash flows from the project.

Exhibit 4.
Expected Annual Cash Flows

END OF YEAR (in $000s)
____________________________________________________________________

Period 0 1 2 3 4 5

Net cash flows ( 900.00) 299.99 340.02 233.32 206.68 180.00


For an estimated initial cash outlay of $900,000, the firm expects to generate net cash flows of
$299,990, $340,020, $233,320, $206,680, and $180,000 over the next five years. The firm's
weighted-average cost of capital is 13 percent. Given this "base case" data, the net present value
is $17,920. The typical capital budgeting response to the project's positive net present value
would be to signal project acceptance. However, given the uncertain estimates for two of the
three ICO components, i.e., shipping and installation, we suggest that the capital budgeting
analyst should defer an accept/reject decision until those uncertain estimates and their multi-year
spillover effects are subjected to sensitivity analysis.

IV.B. Sensitivity Analysis

Sensitivity analysis can be applied to our equipment purchase's uncertain ICO components to
answer a few "what if" questions. What if, for example, our $100,000 estimate for shipping cost
turns out to be higher/lower? And, what if installation is higher/lower than the $200,000 we
originally thought?

To answer those "what if" questions, we first perform new NPV calculations in which we change
our two variables of concern (shipping and installation) individually by, for example,
-30%, -20%, -10%, +10%, +20%, and +30%. Note that changes in these variables have multi-
period spillover effects on depreciation, which affects taxes and future cash flows. Thus, the
change in the ICO not only affects the Year-0 cash flow, but it also affects the cash flows in the
subsequent years.











11



Exhibit 5 compares the estimated NPVs for the different levels of ICOs.

Exhibit 5.
Sensitivity analysis for the equipment purchase showing the impact of individual changes
in two initial cash outlay components on the project's net present value (NPV) in
thousands of dollars


CHANGE IN ORIGINAL INSTALLATION COST
_____________________________________________________

-30% -20% -10% Base +10% +20% +30%

Resulting NPV 58.93 45.27 31.58 17.92 4.25 ( 9.43) (23.09)


CHANGE IN ORIGINAL SHIPPING COST
_____________________________________________________

-30% -20% -10% Base +10% +20% +30%

Resulting NPV 38.43 31.53 24.75 17.92 11.08 4.25 ( 2.59)

From Exhibit 5, we can see that if estimated installation cost were to increase by roughly 13
percent or more from the base case, our project's net present value turns negative. For shipping
cost, however, the increase would need to be roughly 28 percent or more before the project has a
negative net present value.

The data contained in Exhibit 5 can also be presented graphically in an NPV sensitivity graph -
see Exhibit 6. Notice the two "sensitivity lines" in the NPV sensitivity graph. The "installation
cost" line has the steepest slope. Therefore, NPV is more sensitive to equal percentage changes
in that variable than in "shipping cost." Based on this information, management may want to
concentrate more control efforts on the seemingly more critical "installation cost" variable. It
may even want to try and negotiate a fixed-cost price contract for installation from a third party.













12




Exhibit 6: NPV Sensitivity Graph for the Equipment
Purchase



60
50
40
30
20
10
0
(10)
(20)
(30)
Installation cost
Shipping cost
-30 -20 -10 Base 10 20 30

CHANGE IN VARIABLE FROM BASE VALUE (%)



One potential problem with our sensitivity analysis, so far, is that it has looked at sensitivity
"one variable at a time." We can also judge the sensitivity of NPV to simultaneous changes in
two variables by constructing an NPV sensitivity matrix. Exhibit 7 is one such sensitivity matrix
that depicts NPV results for combinations of changes in our two input estimates - "shipping
cost" and "installation cost." Note that a simultaneous cost increase approaching 10 percent for
both shipping and installation costs would result in a negative net present value.

















13
(
$
O
O
O
s
)


N
E
T

P
R
E
S
E
N
T

V
A
L
U
E

A
T

1
3
%





Exhibit 7.
Sensitivity matrix for the equipment purchase showing the impact of simultaneous changes
in two initial cash outlay components on the project's net present value (NPV) in thousands
of dollars


CHANGE IN SHIPPING COST
-30% -20% -10% Base +10% +20% +30%


-30% 79.44 72.60 65.77 58.93 52.10 45.27 38.43

-20% 65.77 58.93 52.10 45.27 38.43 31.58 24.75

-10% 52.10 45.27 38.43 31.58 24.75 17.92 11.08

Base 38.43 31.58 24.75 17.92 11.08 4.25 (2.59)

+10% 24.75 17.92 11.08 4.25 (2.59) (9.43) (16.25)

+20% 11.08 4.25 (2.59) (9.43) (16.25) (23.09) (29.93)

+30% (2.59) (9.43) (16.25) (23.09) (29.93) (36.77) (43.60)


Sensitivity analysis, as we have seen, provides useful and easily understood insights into how a
project's NPV responds to a change in one (or more) uncertain ICO input variables. Thus, the
analysis provides insights into the risk-return trade-off for the project. Given the risk-return
profile in Exhibit 7, should the project be taken? In other words, is the expected NPV of
$17,920 worth the risk of two simultaneous 30% cost overruns, which would result in $43,600
loss? Although there is no theoretically definitive answer, if the possible loss is small relative to
the size of the company, then the risk is probably worth taking, given that the project has a
positive expected value. If the loss is so large that it is a "bet the company" proposition, then the
board of directors should make the final decision.

Sensitivity analysis does not provide any absolute rules for deciding whether or not to accept the
project, but it does provide some clear guidelines regarding the need for a project to be re-
evaluated. For the project in this example, a re-approval analysis should be triggered when the
combined shipping and installation cost overrun is $26,213 or more, since this leads to an
expected negative NPV.
10
In fact, if cost overruns approach $26,213, then the company's
managers should consider possible interventions that might help salvage the value of the project.

10


A $26,213 combined shipping/installation cost overrun corresponds to the region in grey in
Exhibit 7 which indicates negative NPVs. This "break-even" overrun can be calculated as:
(Base NPV)/[1 - T(PVDepr
n,r
)].
14
C
H
A
N
G
E

I
N

I
N
S
T
A
L
L
A
T
I
O
N

C
O
S
T






V. Summary and Conclusions

In a typical capital budgeting analysis, a project's initial cash outlay (ICO) is generally treated as
a single, certain cash outflow. However, upon closer inspection, one or more of the following
conditions may hold true in "real life":

• The ICO may have several cash outflow components - e.g., land, land improvements,
buildings, machinery and equipment.
• Some of the ICO components may be certain cash flows and some may be uncertain/risky
cash flows.
• Some ICO components may be capitalized, but not subject to tax depreciation (e.g.,
land). An outflow like this is already "after-tax" and provides no depreciation tax-shield
benefits that would affect future after-tax operating cash inflows.
• Other ICO components may also be capitalized, but would be subject to tax depreciation
(e.g., land improvement, buildings, machinery and equipment). These outflows will have
spillover effects on future operating cash inflows because of their depreciation tax shield.
• Some ICO component flows may occur after time period zero.

Given these "real life" complicating factors involving a project's ICO, we recommend that
sensitivity testing be applied to uncertain ICO components at the project-evaluation stage. Based
on this sensitivity testing, the firm can then better decide whether to: a) subject any ICO
component estimates to further refining/review; b) remove any ICO component uncertainty by
negotiating a fixed price contract for some service; c) outsource some in-house, uncertain ICO
cost item; or d) accept/reject the project based on the currently available information. The firm
can also identify the critical levels of cost overruns that should trigger a formal re-approval of
the project.





















15



References


Bierman, Harold, "Capital Budgeting in 1992: A Survey," Financial Management, Autumn,
1993, 24.

CFO Executive Board, "Capital Expenditure Re-Approvals," Corporate Executive Board, April
2005.

Daves, Phillip, and Michael Ehrhardt, "Capital Budgeting: The Valuation of Unusual, Irregular,
or Extraordinary Cash Flows," Financial Practice and Education, Vol. 10, No. 2,
Fall/Winter 2000, 106-114.

Graham, John R., and Campbell R. Harvey, "The Theory and Practice of Corporate Finance:
Evidence from the Field," Journal of Financial Economics, Vol. 60, No. 2-3, 2001, 187-
243.



































16

doc_779331119.docx
 

Attachments

Back
Top